Oracle Spends $28.5 Billion A Quarter Building. Who Covers The Wait?

ORCLYTD-43.1%SPYYTD+6.2%QQQYTD+4.2%
Analyze ORCL →

Today’s big story: Anthropic Below Its IPO Price: Do Giants Come Back?

Oracle‘s stock closed Tuesday 67% below its peak. Every data center has a gap between paying for it and getting paid for it. For Oracle, that gap is the whole story. Today’s big story asks whether Oracle should keep building or take a breather. Here we ask who covers the wait.

Image from Pixabay

How Long Is Oracle’s Wait?

A data center comes together in three steps. First, a developer builds the shell and brings in power. For the first buildings at Oracle’s flagship site in Abilene, Texas, that took more than a year. Next, Oracle fills the building with chips, servers and networking. Then the customer starts paying, under contracts that mostly run up to five years.

Oracle says it buys the equipment very late in the build. It says the stretch of costs without sales is “on the order of a couple of months.” Its balance sheet shows more. Oracle holds $48.5 billion of equipment and fit-out it has bought but not yet put to use. Capital spending is money put into long-lived assets such as data centers. Oracle’s was $28.5 billion in the latest quarter. At that pace, the unused equipment equals about five months of spending. At the past year’s pace, it equals about eight months.

Who is covering Oracle’s wait?

1 Landlords: $288 billion of rent, over 15 to 19 years, on data-center leases not yet started. Oracle pays nothing until each building is delivered.
2 Customers: $16 billion paid in advance over the past two quarters; others bring their own chips.
3 Lenders: borrowing up from $84.5 billion to $125.3 billion in the two years to August, and $10 billion more in November.
4 Suppliers: unpaid building bills up from $1.6 billion to $6.2 billion.
5 Shareholders: $25 billion of new stock sold in the year to August, and $10 billion more in November.

Source: Trefis, from Oracle’s filings. Leases, prepayments and unpaid building bills cover Aug 2024 to Aug 31, 2026. Borrowing and new stock come from quarterly balance sheets and cash flows, and Oracle’s Nov 4 filing.

Oracle has $48.5 billion of equipment it has bought but not yet put to use. Its stock is 67% below its peak. If you hold it through that wait, it helps when part of your savings brings in cash now. The Trefis Income Solution owns 50 companies that have each paid dividends for at least 10 years in a row, and together they yield about 3 times what the S&P 500 pays. See the Income Solution.

Can Oracle Make Customers Carry More?

It already does. In the quarter to August, customers paid Oracle $11.4 billion in advance. The quarter before, they paid $4.6 billion. The money Oracle has collected for services not yet delivered doubled to $30.8 billion. That is most of why its operating cash flow jumped to $23.1 billion in the quarter. Operating cash flow is the cash its business brings in. A year earlier, it was $8.1 billion. Oracle’s finance chief said the “vast majority” of new contracts were prepaid or used the customer’s own hardware.

There are limits. Only customers with cash can pay ahead. The biggest AI buyers are spending nearly everything they bring in. A prepayment is not free, either. Oracle’s filings say these deals come with a “significant financing component.” So Oracle records an interest cost on them, which is small so far. And it repays the customer in computing time, not cash. In effect, it is a loan from the customer. It is quieter than a bond, but it is still a loan.

What Gap Does Oracle Keep?

Oracle has handed the wait during construction to landlords and customers. What it keeps is a longer gap. Its new data-center leases run 15 to 19 years. It has $664 billion of signed future business, and 84% of it is due to turn into sales within five years. Oracle’s own annual report says the leases “typically do not align with the duration and pricing of customer contracts.”

Who pays the rent in years six to 19 if customers don’t renew? Oracle. No one else has agreed to cover that gap.

What Will Oracle’s December Report Show?

So far, the payback is slow. Since mid-2024, Oracle has put $105 billion into capital spending. More than $40 billion of it is not yet in use. Over the same stretch, its yearly sales are up $19 billion.

Oracle’s next report, in December, will show three things. One is whether customers kept paying ahead. Another is how much of the capital spending Oracle paid for itself after prepayments. The third is how much of the $288 billion of leases has started to show up as rent. If customers keep carrying the wait, the debt can stay manageable, in our view. If they stop, the gap comes back to Oracle’s balance sheet.

We looked at how far Oracle’s spending runs past its cash in Why Is Oracle Spending $1.61 For Every Cash Dollar? Another AI cloud, CoreWeave, faces its own choice about building. We look at it in CoreWeave Stock At $43: What If It Just Stops Building?

A lot rides on whether Oracle’s customers keep paying ahead. That is a reason to own many strong companies, not just one. Then no single wait decides how you do.

Why Own One Leader When You Can Own 30?

If you like finding quality companies like Oracle, the Trefis High Quality (HQ) Portfolio holds 30 of them in equal weight, and has returned more than 105% since its September 2020 launch. You’re welcome to look inside.

See The HQ Portfolio

For education, not a recommendation to buy or sell.

For questions about this article or underlying research, email help@trefis.com.